In force in Maine

Fire, building, elevator, boiler and pool codes in force in Maine now.

Who enforces each one, what edition applies, and what changes next. 5 of 8 state-level topic areas checked against primary sources. OSHA state plan for public employers only; private employers under federal OSHA.

Explore Maine by location and topic

By topic in Maine

One page per area

In force in Maine now

Statewide · county and city rules sit on top
AreaIn forceAuthorityNext
FireNFPA 101 Life Safety Code (2018 ed.) via fire marshal rule 16-219 CMR ch. 20 + NFPA 1 Fire Code (2018 ed.) via ch. 3, as listed on the State Fire Marshal rules page (listing only; adopted rule text not read)Rules page listing: Chapter 20 (amended Jan 25, 2021) adopts NFPA 101 (2018), NFPA 80 (2019), 220, 221, 241; Chapter 3 (amended Nov 27, 2019) adopts NFPA 1 (2018). 25 MRSA 2452 (read) has the Commissioner of Public Safety adopt rules on safety to life from fire; violation of a rule is a Class E crime. SourceReported, in verificationOffice of State Fire Marshal, Dept. of Public Safety; Commissioner of Public Safety adopts the rules (25 MRSA sec.2452)In forceIn force; State Fire Marshal rules page (re-read Oct 27, 2026) lists Ch. 20 amended Jan 25, 2021 (NFPA 101-2018) and Ch. 3 amended Nov 27, 2019 (NFPA 1-2018), and names no chapter under revision; adopted rule text could not be confirmed on the primary page
BuildingMUBEC: 2021 IBC, IEBC, IRC, IECC and IMC with ASHRAE 62.1, 62.2 and 90.1 (2019), per the MUBEC Standards and Amendments document, effective beginning April 7, 202510 MRSA 9724 (read): municipalities with more than 4,000 residents must enforce MUBEC; smaller towns need not, and may not adopt or enforce another building code. Conflicting local ordinances are void, with exceptions. The MUBEC Standards document also lists ASTM E1465-2008 radon control for new low-rise residential buildings. Municipal code offices handle permits and inspections. SourceChecked on the sourceMunicipal building officials enforce MUBEC (mandatory at 4,000+ population); Technical Building Codes and Standards Board / Office of Community Affairs sets the code statewideIn forceIn force (Building Codes page read Oct 27, 2026: amended MUBEC adoption enforced as of April 7, 2025; 2021 IRC, IBC, IEBC, IECC, IMC; no 2026 amendment listed; the codes division moved to the Maine Office of Community Affairs)
ElevatorsRule 02-041 ch. 511 (national codes); editions in force reported as ASME A17.1-2013, A17.3-2011 and A18.1-2014; repeal-and-replace proposed (A17.1-2022, A17.3-2023, A18.1-2023), effective date pending32 MRSA 15221 (read): annual inspection; certificate posted in the elevator; an inspector may suspend a certificate for a safety menace. Program page (read Oct 20, 2026): ch. 511 repeal-and-replace first advertised Dec 3, 2025; revised proposal puts elevators installed before Jan 1, 2003 under A17.3-2023, with five years to comply after the pending effective date. SourceReported, in verificationDirector, Office of Professional and Occupational Regulation (Dept. of Professional and Financial Regulation), Elevator and Tramway Safety ProgramRulemaking pendingWatch: program page (read Oct 26, 2026) still describes the ch. 511 repeal-and-replace as proposed; revised-proposal comments closed May 8, 2026; no effective date stated
BoilersBoiler/pressure-vessel certificate program under 32 MRSA c.131; certificates valid up to 14 months (boilers) or 38 months (pressure vessels)32 MRSA 15117 (read): inspection certificates may be valid up to 14 months for a boiler and up to 38 months for a pressure vessel, measured from inspection. The chief inspector issues certificates; the chief inspector, a deputy inspector or an authorized inspector performs inspections and may suspend a certificate for unsafe units. SourceChecked on the sourceDirector and chief inspector under 32 MRSA c.131; deputy and authorized (insurer) inspectors perform inspections; statewideIn force
PoolsPublic pools/spas licensed under 22 MRSA c.562 (DHHS); compliance inspection at least every 2 years22 MRSA 2497 (read): the department must determine compliance with chapter 562 and its rules at least once every two years, by inspection or another method it chooses. It may enter licensed premises at reasonable times without an administrative inspection warrant. Licensing steps and fees are in other sections. SourceChecked on the sourceDept. of Health and Human Services (Maine CDC health-inspection program), statewideIn force
LodgingLodging places licensed by DHHS (22 MRSA c.562, 2-year inspection cycle); hotels/high-rises need sprinklers (built after 1992) or detection systems (existing, since 1981) under 25 MRSA sec.246325 MRSA 2463 (read): hotels (more than 15 sleeping rooms) built after Jan 1, 1992 with 2+ stories need a sprinkler system; other 2+ story hotels need a detection system (stated deadline Jul 1, 1981). The Commissioner of Public Safety or designee inspects and approves, or the municipal fire department where one exists. DHHS 2-year compliance check: 22 MRSA 2497. SourceChecked on the sourceDept. of Health and Human Services (licensing/inspection), statewide; Office of State Fire Marshal for sprinkler/detection complianceIn force
WorkplaceFederal OSHA covers private employers; Maine State Plan covers only state/local government employeesOSHA page (read): the Maine State Plan covers state and local government workers (initial approval Aug 5, 2015; certification Mar 21, 2023). It does not cover federal workers or private-sector employers, which remain under federal OSHA. SourceChecked on the sourceFederal OSHA (private sector); Maine Dept. of Labor / Maine State Plan (public-sector employees only)In force
EnvironmentalMaine layer: asbestos abatement over 3 linear or 3 square ft needs written notice to DEP, postmarked 10 calendar days or delivered 5 working days before on-site work (38 MRSA 1273). Building demolition: DEP notice at least 5 working days before (not single-family homes), even if no asbestos found; licensed asbestos consultant inspection for most non-residential buildings (DEP demolition page). Underground oil tanks: registered at least 10 business days and no more than 2 years before installation; $100 per tank, billed every 3 years; annual inspection results to DEP by July 1; amended registration immediately upon a change, late period up to 10 business days if set by rule (38 MRSA 563). Reported, not re-read: wastewater overflow reporting within 24 hours (Chapter 523). Federal EPA rules also apply38 MRSA 1273 does not mention demolition or consultant inspection. DEP air pages not read: generator and boiler licensing/exemptions (Chapter 115, 169) are unconfirmed; a search shows emergency generators under 1,000 bhp treated under Chapter 169 in facility licenses. Statewide grease, lift-station and backflow rules not located; local utilities and plumbing code may apply. SourceReported, in verificationMaine Department of Environmental Protection (asbestos, USTs, air licensing, wastewater licenses); U.S. EPA; local sewer districts and municipalities for grease, lift-station and backflowDeadline Mar 1, 2027Federal dates: Tier II filing Mar 1, 2027; HFC leak detection Jan 1, 2027. Annual UST inspection results due to DEP by Jul 1. Generator/boiler air licensing: confirm with DEP Air Licensing

Dated items in Maine

Next 24 months
Jan 1, 2027
Automatic leak detection on existing 1,500 lb+ HFC commercial refrigerationFederal EPA · 40 CFR 84.108
Confirmed date
Mar 1, 2027
EPCRA Tier II chemical inventory filingFederal EPA · 40 CFR 370.45
Confirmed date
Jul 1, 2027
Annual underground oil tank and piping inspection results due to DEPMaine DEP · 38 MRSA 563
Confirmed date

Recent changes to the Maine record

Since October 20, 2026 · all states

What our record said before and after each change, with the date and the official source. A change to the record is not by itself a change in the law: an edition, a date or a source may have been corrected or made more precise. Confirm the current text with the authority.

2026-10-26
Elevators · Source
Before: https://www.maine.gov/pfr/professionallicensing/professions/elevator-tramway-safety-program
After: https://www1.maine.gov/pfr/professionallicensing/professions/elevator-tramway-safety-program
source · as recorded in our state record on 2026-10-26
2026-10-26
Building · Next
Before: In force (MUBEC Standards document read Oct 21, 2026: effective beginning April 7, 2025); proposed-rule status could not be confirmed on the primary page
After: In force (Building Codes page read Oct 26, 2026: amended MUBEC adoption enforced as of April 7, 2025; 2021 IRC, IBC, IEBC, IECC, IMC; no 2026 amendment listed; the codes division moved to the Maine Office of Community Affairs)
source · as recorded in our state record on 2026-10-26
2026-10-26
Building · Source
Before: https://www.maine.gov/dps/fmo/sites/maine.gov.dps.fmo/files/inline-files/MUBEC%20Standards%20and%20Amendments.pdf
After: https://www1.maine.gov/dps/fmo/building-codes
source · as recorded in our state record on 2026-10-26
2026-10-21
Environmental · In force
Before: Maine layer: asbestos abatement over 3 linear or 3 square ft needs written notice to DEP, postmarked 10 calendar days or delivered 5 working days before on-site work (38 MRSA 1273, read). Underground oil tanks: registered at least 10 business days and no more than 2 years before installation; fee $1
After: Maine layer: asbestos abatement over 3 linear or 3 square ft needs written notice to DEP, postmarked 10 calendar days or delivered 5 working days before on-site work (38 MRSA 1273). Building demolition: DEP notice at least 5 working days before (not single-family homes), even if no asbestos found; l
source · as recorded in our state record on 2026-10-21
2026-10-21
Building · In force
Before: MUBEC: 2021 IBC, IEBC, IRC, IECC and IMC with ASHRAE 90.1 and 62 (2019), per the MUBEC Standards and Amendments document effective April 7, 2025 (reported; standards PDF not read)
After: MUBEC: 2021 IBC, IEBC, IRC, IECC and IMC with ASHRAE 62.1, 62.2 and 90.1 (2019), per the MUBEC Standards and Amendments document, effective beginning April 7, 2025
source · as recorded in our state record on 2026-10-21
2026-10-20
Fire · In force
Before: NFPA 101 Life Safety Code (2018 ed.) via fire marshal rule 16-219 CMR ch. 20 + NFPA 1 Fire Code (2018 ed.) via ch. 3, as listed on the State Fire Marshal rules page (search listing; page itself returned 403)
After: NFPA 101 Life Safety Code (2018 ed.) via fire marshal rule 16-219 CMR ch. 20 + NFPA 1 Fire Code (2018 ed.) via ch. 3, as listed on the State Fire Marshal rules page (listing only; adopted rule text not read)
source · as recorded in our state record on 2026-10-20
2026-10-20
Elevators · In force
Before: Rule 02-041 ch. 511 (national codes); editions reported as ASME A17.1-2013, A17.3-2011 and A18.1-2014; a repeal-and-replace adopting A17.1-2022, A17.3-2023 and A18.1-2023 is pending
After: Rule 02-041 ch. 511 (national codes); editions in force reported as ASME A17.1-2013, A17.3-2011 and A18.1-2014; repeal-and-replace proposed (A17.1-2022, A17.3-2023, A18.1-2023), effective date pending
source · as recorded in our state record on 2026-10-20

Questions about Maine

Which fire code is in force in Maine?

NFPA 101 Life Safety Code (2018 ed.) via fire marshal rule 16-219 CMR ch. 20 + NFPA 1 Fire Code (2018 ed.) via ch. 3, as listed on the State Fire Marshal rules page (listing only; adopted rule text not read). Rules page listing: Chapter 20 (amended Jan 25, 2021) adopts NFPA 101 (2018), NFPA 80 (2019), 220, 221, 241; Chapter 3 (amended Nov 27, 2019) adopts NFPA 1 (2018). 25 MRSA 2452 (read) has the Commissioner of Public Safety adopt rules on safety to life from fire; violation of a rule is a Class E crime. Enforced by: Office of State Fire Marshal, Dept. of Public Safety; Commissioner of Public Safety adopts the rules (25 MRSA sec.2452).

Which building code applies in Maine?

MUBEC: 2021 IBC, IEBC, IRC, IECC and IMC with ASHRAE 62.1, 62.2 and 90.1 (2019), per the MUBEC Standards and Amendments document, effective beginning April 7, 2025. 10 MRSA 9724 (read): municipalities with more than 4,000 residents must enforce MUBEC; smaller towns need not, and may not adopt or enforce another building code. Conflicting local ordinances are void, with exceptions. The MUBEC Standards document also lists ASTM E1465-2008 radon control for new low-rise residential buildings. Municipal code offices handle permits and inspections. Enforced by: Municipal building officials enforce MUBEC (mandatory at 4,000+ population); Technical Building Codes and Standards Board / Office of Community Affairs sets the code statewide.

Who inspects elevators and boilers in Maine?

Elevators: Director, Office of Professional and Occupational Regulation (Dept. of Professional and Financial Regulation), Elevator and Tramway Safety Program (Rule 02-041 ch. 511 (national codes); editions in force reported as ASME A17.1-2013, A17.3-2011 and A18.1-2014; repeal-and-replace proposed (A17.1-2022, A17.3-2023, A18.1-2023), effective date pending). Boilers: Director and chief inspector under 32 MRSA c.131; deputy and authorized (insurer) inspectors perform inspections; statewide (Boiler/pressure-vessel certificate program under 32 MRSA c.131; certificates valid up to 14 months (boilers) or 38 months (pressure vessels)).

Is Maine a federal OSHA state or a state-plan state?

Maine runs an OSHA-approved state plan that covers state and local government employers only (Maine State Plan (public-sector employees only)). Private employers, including hotels and commercial buildings, answer to federal OSHA.

What changes next in Maine?

Elevators: Rulemaking pending (Watch: program page (read Oct 26, 2026) still describes the ch. 511 repeal-and-replace as proposed; revised-proposal comments closed May 8, 2026; no effective d); Environmental: Deadline Mar 1, 2027 (Federal dates: Tier II filing Mar 1, 2027; HFC leak detection Jan 1, 2027. Annual UST inspection results due to DEP by Jul 1. Generator/boiler air licensing: co); Jan 1, 2027: Automatic leak detection on existing 1,500 lb+ HFC commercial refrigeration; Mar 1, 2027: EPCRA Tier II chemical inventory filing.

Free reference. No account is needed. Membership — Coming soon.